The Dubai Metro Blue Line, a 20.5‑billion‑dirham project, is now 30 percent complete, according to Sheikh Hamdan bin Mohammed, Crown Prince of Dubai, who visited the site on Sunday. He said the line will add 30 km to the network, 15.5 km of which will be underground, and will include 14 new stations. The project will connect Bur Dubai/Deira, Downtown/Business Bay, Dubai Silicon Oasis, Dubai Marina/JBR and Expo City Dubai.
Progress and workforce
Sheikh Hamdan noted that 14,000 workers, engineers and supervisors have logged 33 million working hours. The workforce is driving the project toward its scheduled opening on 9 September 2029, the 20th anniversary of the original Dubai Metro launch.
Work is gathering pace ahead of the scheduled opening on 9 September 2029.
Design and future plans
During the visit, the Crown Prince was briefed on the sleek new train design and modern interiors, as well as the striking station interiors. The Blue Line will extend the total network to 131 km with 78 stations, served by 168 trains. Dubai also unveiled a 34‑billion‑dirham Gold Line in April, aimed at serving 1.5 million residents.