Iran’s state electricity operator, Tavanir, has started imposing scheduled power cuts because it cannot supply enough fuel to power plants.
Tavanir chief executive Mohamad Allahdadi told state TV that the cuts would last up to two hours every other day, and could extend to two hours each day if temperatures fall further.
He added that the length of the outages would depend on fuel supplies and how well consumers manage their energy use.
The attack on the country's gas infrastructure has aggravated the situation, and we should therefore expect difficulties this winter - Masoud Pezeshkian, Iranian President
Gas processing capacity remains damaged
President Masoud Pezeshkian said on Saturday that attacks on the country’s gas infrastructure have worsened the energy crisis.
"The attack on the country's gas infrastructure has aggravated the situation, and we should therefore expect difficulties this winter," Pezeshkian was quoted as saying by the Isna news agency.
Iranian officials reported that March 17 strikes damaged four gas‑processing sites at the South Pars field, cutting about 230 million cubic metres of daily capacity.
Only 100 million cubic metres have been restored, leaving roughly 130 million cubic metres offline.
Winter shortfall expected to hit 430 million cubic metres
Government spokeswoman Fatemeh Mohajerani warned that the country could face a gas shortfall of 430 million cubic metres per day this winter.
This is higher than the roughly 300 million cubic metres shortfall seen in previous years.