Iran's state mining agency IMIDRO has outlined $9 billion in industrial and mining projects to expand its copper sector. It expects the plan to lift annual production of copper cathode to 500,000 tons.
The country now produces 300,000 tons of cathode a year. The new target would nearly double that, but it still falls short of the 800,000-ton goal set in Iran's Seventh Development Plan.
IMIDRO head Mohammad Masoud Samiinejad said completing the value chain and downstream industries is the agency's top priority. He noted that some mining projects have already reached their capacity under the development plan.
"For the development of the copper industry, $9 billion in industrial and mining projects has been defined, and we predict that with the implementation of these projects, we will achieve an annual production of 500,000 tons of copper cathode.", Mohammad Masoud Samiinejad, head of IMIDRO
Foreign currency shortages have forced Iran to pause some projects. The focus is now on finishing those that are more than 70 percent physically complete, so they can start operating by the end of the current government's term.
Samiinejad said IMIDRO will not supply raw materials or offer bank loans to investors. They must use their own funds. The agency will instead provide infrastructure such as electricity, gas and roads for small-scale mines.
Private exploration is backed by the Mining Activities Investment Insurance Fund. If a project fails to find minerals, the investor can claim compensation.