Bulldozers have started digging the £800‑million Havant Thicket reservoir near Portsmouth as Britain confronts persistent drought after a record‑breaking summer heat wave.
The Environment Agency reported that by mid‑November almost all of England remained in drought, with many areas classified as severe and existing reservoirs only 60 % full, 19 points below the seasonal average.
Portsmouth Water chief executive Bob Taylor said the project reflects the water industry’s response to successive droughts and the need to store winter rain for use in increasingly dry summers.
"We've got increasing problems with our water security in the UK," climate scientist Hannah Cloke said.
Capacity and timeline
When completed, the reservoir will hold up to 8.7 billion litres of water, enough to supply hundreds of thousands of people and deliver up to 111 million litres per day alongside a pending wastewater‑recycling plant.
Taylor said the reservoir is expected to become operational in 2032 or 2033, making it the first new reservoir in England since 1992.
The government has approved nine major reservoirs by 2050, which together could add 670 million litres per day to national supplies.
Policy backdrop
England’s 2025 National Framework for Water Resources projects a daily shortfall of five billion litres by 2055 as population growth and water‑intensive industries, such as data centres, increase demand.
Climate scientist Hannah Cloke of Reading University warned that water‑security problems will worsen without improved storage, noting that extreme weather events are becoming more frequent and intense.